The State of Kansas is proposing to dredge John
Redmond Reservoir to restore water supply lost to sedimentation.
Information on the project purpose, schedule, funding, public
meetings and more will be continuously added to this website. In
addition, the responses to several Frequently Asked Questions (FAQs)
will be added to this website.
Kansas Water Office
Communications Director
901 S. Kansas Avenue
Topeka, KS 66612
Katie.Ingels@kwo.ks.gov
(785) 296-3185

Current Activity
The Kansas Water Office has initiated a request to dredge John Redmond through meetings and conservations with the U.S. Army Corps of Engineers, in 2012-2013, KWO will be collecting additional data, completing the necessary environmental documentation, and conducting several stakeholder and public outreach meetings about the project. All documents developed and meetings scheduled will be posted to this website.
The two key documents the Kansas Water Office will be developing for the dredging activity include:
Request for permission to alter/modify a Corps project (33 USC 408)
National Environmnetal Policy Act (NEPA) - Programmatic Environmental Impact Statement
Request for Proposals
The Kansas Water Office sought proposals for the design-dredge of John Redmond Reservoir through March 19, 2013. The Scope of Work for this project is to provide a plan with a proposed process, schedule and estimted costs for completing engineering, acquisition of permits, construction of disposal facilities, mobilization and demobilization, dredging and land reclamation. KWO is reviewing the proposals submitted and anticipates awarding a contract in May 2013. Successful bid teams will be identified on this website.
Meetings
February 5, 2013 - 9:30 a.m., Meeting at Coffey County Courthouse, Burlington, KS for Dredging John Redmond - Press Release - Meeting Materials
February 5, 2013 - 11:00 a.m., Pre-Proposal Conference for the Design Dredge at John Redmond; Coffey County Courthouse (110 S. 6th St.) Burlington, Kansas - Meeting Materials
December 3, 2012 - Coffey County Commission, Burlington, KS
September 4-6, 2012 – KWO met with U.S. Army Corps of Engineers to identify the process for dredging a federal project
April 17-19, 2013 - KWO presented at the Western Dredger's Association meeting, Midwest Chapter in St. Louis, MO - Presentation
Sources
For interested bidders - A topographic/LidAR image and Soils Map are provided as an example site for the location of the Confined Disposal Facility. Refer to Questions Regarding the Design-Dredge for John Remond Reservoir Request for Proposals link below for additional clarification. This site is an example only for bidding purposes. Actual sites for disposals will be identified by the Kansas Water Office.
Lake Level Management Plan for John Redmond Reservoir, Water Year 2013
Bathymetric Survey of John Redmond Reservoir, Coffey County, Kansas
Enhanced Riparian Area/Stream Channel Assessment for John Redmond Feasibility Study
Project Management Plan John Redmond Dam and Reservoir, Kansas Watershed Feasibility Study (copy available upon request)
Reservoir Roadmap, Vollume III - Neosho Basin Approach to Reservoir Sustainability
Sediment Loads to John Redmond Reservoir by Contributing Area
Frequently Asked Questions (FAQs)
1.Are any alternatives to dredging being considered?
Many short and mid-term alternatives to reduce sedimentation at the
lake or increase storage have already or are currently being
implemented. Streambank restoration projects on the Neosho and
Cottonwood Rivers will decrease the amount of new sediment delivered
downstream to John Redmond. After many years of negotiations, a
2-foot pool raise and reallocation of storage is anticipated at the
reservoir in 2013. This pool raise will increase the storage
available for water supply by approximately 20,000 AF. While these
actions have been important steps to extending the life of the
reservoir, removal of the already deposited sediment is necessary to
ensure a reliable water supply is available to meet the current and
future area demands.
Other alternatives to dredging that have been evaluated include
construction of a pipeline to transfer water from other areas of the
state or region and development of a new reservoir. Based on cost
and feasibility, the dredging alternative has been determined to be
a more viable alternative.
2. Who will pay for this dredging activity?
Costs for dredging would be borne solely by the state or other non-federal partners and would include planning, permits and studies, land acquisition, dredged materials disposal area and dewatering area construction, dredging, and disposal management.
3. How much sediment will be removed?
The plan is to remove sediment at a pace and purpose to maintain storage for current demands. Depending on whether dredging is conducted continuously or as a phased approach, about 600,000 cubic yards would be removed each year.
4. How long will it take to dredge John Redmond?
Because the goal of the dredging is to restore and maintain storage into the future, removal of sediment will take up to 25 years.
5. Where will the dredged sediment be placed?
Dredged materials will be placed in uplands within a reasonable hauling/pumping distance from the reservoir. The Kansas Water Office is seeking feedback from landowners in Coffey County and surrounding areas who may be interested and willing to accept the materials on their property.
6. How can I share my comments or concerns about this activity?
Your feedback and comments are important to the
success of this activity. You can provide comments through public
scoping meetings (see list of meetings) or contacting the Kansas
Water Office:
Kansas Water Office
Communications Director
901 S. Kansas Avenue
Topeka, KS 66612
Katie.Ingels@kwo.ks.gov
(785) 296-3185